Town Hall Tuesday – Week 70

08/05/2018

So much has been happening in the last month… it really is coming together!

External

We have completed the new drainage to the west of the building. New road gulleys and a new drainage pipe has been added here as the old drains had collapsed.
The kerbs have been moved 400mm further out into the road and we are now preparing for new paving.

080518 external kerb
The new water main has been installed (the last of the utility services).

Ground floor

We have built the new office wall and are now wiring the electrical supplies into it.

080518 gf office wall
The new glass sliding doors have been installed.

080518 gliding days
The ground floor pod has now been built and plastered. This will be for the toilets and storage.

080518 e columns
The staircase is being painted ready for the new lift to be installed.

080518 lift shaft

First floor

This has now been fully decorated and we have adjusted the chandeliers to be slightly lower than before.

080518 ff red paint
The commercial kitchen is being prepared for new services ready for appliances.

Attic

We are fitting the acoustic boarding to the stairwell area.
The plant room is being fitted out.
The holiday let has now been decorated and the lights have been installed.

080518 attic decorated 080518 attic lighting

Heritage Open Days 2018 – The Big Launch!

14-16 Sept 18

Brackley Town Hall is re-opening after being closed for two years for an extensive restoration. Come inside and see the restoration for yourself. Have a nose inside the office, kitchens, attic and all the public areas for the first time since 2016! No stone, floorboard, window, tile has been left untouched in our £3.2 million … Continue reading Heritage Open Days 2018 – The Big Launch!

More