Town Hall Tuesday – Week 37


It’s been a busy few days, with the new staircase arriving yesterday which means work can now begin on this exciting instalment of the build!

Ground Floor

• The Staircase/Lift shaft steel has been delivered and the bolts installed to hold the legs.

190917-stair-case-legs-with-bolts 190917-staircase-uprights-in-place
• A small crane has been put in the main entrance to start assembling the steel lift shaft.

190917-small-internal-crane-delivered 190917-internal-crane-delivered-aerial 190917-internal-crane-in-situ 190917-internal-crame
• The building’s main services are ongoing
• The plastering to the ground floor main entrance is ongoing.
• Electrical containment ongoing

First Floor

• Services have been installed through the ground floor ceiling into the first floor.

• Paint has been removed from the first-floor ceiling rib.


• The east elevation re-slating is ongoing.

190917-east-elevation-progress 190917-east-elevation-progress 190917-east-elevation-progress-3
• The leadwork to the dormers are being finished.

• Leadwork to clock tower near completion.
• Bellcote has been re-painted, including the bell stock.

190917-bell-cote-and-headstock-painted 190917-bell-tower-repainted
• New lead details to bellcote.


Most of the past week has been preparing for the crane lift tomorrow, which will be lifting the clock mechanism, faces, weather vane and the bells back into the bellcote!

Baa Baa Brackley 2018

21 April 18

Come along to find out about Brackley wool history and present with heritage displays, wool working and local craftspeople. Meet some real sheep! The Sheep Roadshow Local Craftspeople Facepainting Learn to Knit workshops Living History   10-4 in the Old Fire station, Brackley