Town Hall Tuesday – Week 37

19/09/2017

It’s been a busy few days, with the new staircase arriving yesterday which means work can now begin on this exciting instalment of the build!

Ground Floor

• The Staircase/Lift shaft steel has been delivered and the bolts installed to hold the legs.

190917-stair-case-legs-with-bolts 190917-staircase-uprights-in-place
• A small crane has been put in the main entrance to start assembling the steel lift shaft.

190917-small-internal-crane-delivered 190917-internal-crane-delivered-aerial 190917-internal-crane-in-situ 190917-internal-crame
• The building’s main services are ongoing
• The plastering to the ground floor main entrance is ongoing.
• Electrical containment ongoing

First Floor

• Services have been installed through the ground floor ceiling into the first floor.

190917-services-up-to-ff
• Paint has been removed from the first-floor ceiling rib.

Roof

• The east elevation re-slating is ongoing.

190917-east-elevation-progress 190917-east-elevation-progress 190917-east-elevation-progress-3
• The leadwork to the dormers are being finished.

190917-leadwork-on-dormers
• Leadwork to clock tower near completion.
• Bellcote has been re-painted, including the bell stock.

190917-bell-cote-and-headstock-painted 190917-bell-tower-repainted
• New lead details to bellcote.

190917-headstock-bellcote

Most of the past week has been preparing for the crane lift tomorrow, which will be lifting the clock mechanism, faces, weather vane and the bells back into the bellcote!

Town Hall Heritage Group Meeting

16 Oct 18

A group for those interested in keeping the Town Hall heritage alive. This will be our first meeting (Tuesday 16th October in the Town Hall at 7:30pm.) The aims of the group will include communications, looking after the council records and putting on events or tours to celebrate the Town Hall and Brackley’s past. These … Continue reading Town Hall Heritage Group Meeting

More