• 21
    Nov
    Town hall Tuesday – Week 46
    I'm afraid week 45's blog didn't get written as your trusty blogger was suffering from tonisllitis - this week's bumper edition includes images from the last two weeks and...
    More
  • 7
    Nov
    Town Hall Tuesday – Week 44
    This week, three of our volunteer photographers had the opportunity to have a walk around the site and capture the progress of the build. The following is a selection...
    More
  • 1
    Nov
    Town Hall Tuesday – Week 43
    Ground Floor Plastering is being carried out to the stairwell and the new ground floor office. Fire alarm cables and security cables have been installed into the hall ceiling ready for...
    More